slava.energy: UK renewable energy projects
Tormywheel Wind Farm Extension
REPD record 6989. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 1 MW
- Status
- Planning Permission Granted
- Operator
- Muirhall Energy
- County
- West Lothian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- West Lothian
- Planning reference
- LIVE/0226/FUL/17
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-09-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-03-30: Planning Application Submitted
- 2020-03-06: Planning Permission Granted
- 2025-03-06: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6989. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.