slava.energy: UK renewable energy projects
North Wiltshire Biomass Power Plant
REPD record 7. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 5.5 MW
- Status
- Planning Permission Refused
- Operator
- NOVERA
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- 00/01204/EIA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2004-11-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2000-05-24: Planning Application Submitted
- 2001-09-11: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.