slava.energy: UK renewable energy projects
Funtley Refuse Tip (Landfill Gas)
REPD record 700. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Landfill Gas
- Capacity
- 1 MW
- Status
- Planning Permission Expired
- Operator
- Cassidy & Ashton Group Ltd
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Winchester
- Planning reference
- 13/01247/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-09-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-06-05: Planning Application Submitted
- 2013-08-28: Planning Permission Granted
- 2016-08-28: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 700. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.