Nether Moor Field
REPD record 7019. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Operational
- Operator
- Thurcroft Energy (Max Design Consultancy)
- County
- South Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Rotherham
- Planning reference
- RB2017/1426
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-05-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-09-29: Planning Application Submitted
- 2017-12-21: Planning Permission Granted
- 2020-09-01: Operational
- 2022-11-22: Planning Permission Expired
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7019. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.