slava.energy: UK renewable energy projects
Hilfield Farm Tech
REPD record 7030. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Revised
- Operator
- Capbal
- County
- Hertfordshire
- Region
- Eastern
- Country
- England
- Planning authority
- Hertsmere
- Planning reference
- 18/1587/OUT
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-03-26
Status history
Dated status events as published by REPD, release Q3 2026.
- 2018-08-08: Planning Application Submitted
- 2019-05-28: Planning Permission Refused
- 2019-11-13: Appeal Lodged
- 2020-03-24: Appeal Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7030. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.