Enderby Storage, Redcomb Farm
REPD record 7044. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Operational
- Operator
- Statera Energy & Gresham House
- County
- Leicestershire
- Region
- East Midlands
- Country
- England
- Planning authority
- Blaby
- Planning reference
- 17/1223/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-03-06
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-10-13: Planning Application Submitted
- 2018-01-04: Planning Permission Granted
- 2021-04-01: Under Construction
- 2022-01-01: Operational
Open this area on the map