Dungannon Energy Storage System
REPD record 7050. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 50 MW
- Status
- Under Construction
- Operator
- Low Carbon Storage Ireland
- County
- Co. Tyrone
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Mid Ulster
- Planning reference
- LA09/2018/0803/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-03-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2018-06-05: Planning Application Submitted
- 2019-12-01: Under Construction
- 2023-10-07: Planning Permission Expired