Riverford Farm
REPD record 7078. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Planning Permission Expired
- Operator
- Abham Storage & Statera Energy
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- South Hams
- Planning reference
- 3360/17/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-08-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-10-18: Planning Application Submitted
- 2017-12-04: Planning Permission Granted
- 2021-01-05: Planning Permission Expired