slava.energy: UK renewable energy projects
Long Lands Lane
REPD record 7079. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 12 MW
- Status
- Abandoned
- Operator
- Tiger Energy
- County
- South Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Doncaster
- Planning reference
- 17/02562/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-02-26
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-10-16: Planning Application Submitted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7079. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.