slava.energy: UK renewable energy projects
Severn Road
REPD record 7085. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 32 MW
- Status
- Operational
- Operator
- FPC Industry & Enterprise
- County
- Gloucestershire
- Region
- South West
- Country
- England
- Planning authority
- Bristol, City of
- Planning reference
- PT17/4664/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-10-13
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-10-05: Planning Application Submitted
- 2018-02-21: Planning Permission Granted
- 2021-08-01: Under Construction
- 2021-12-23: Operational
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7085. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.