Grendon Storage
REPD record 7089. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Planning Permission Expired
- Operator
- Statera Energy & Grendon Storage
- County
- Northamptonshire
- Region
- East Midlands
- Country
- England
- Planning authority
- North Northamptonshire
- Planning reference
- WP/17/00602/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-08-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-09-28: Planning Application Submitted
- 2017-11-20: Planning Permission Granted
- 2021-05-01: Planning Permission Expired