Facts
As published by REPD, release Q3 2026.
- Technology
- Landfill Gas
- Capacity
- 2.9 MW
- Status
- Operational
- Operator
- ONYX
- County
- Greater Manchester
- Region
- North West
- Country
- England
- Planning authority
- Oldham
- Planning reference
- 40861
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2004-12-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2001-01-02: Planning Application Submitted
- 2001-10-11: Planning Permission Granted
- 2003-09-25: Operational
- 2012-10-11: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 709. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.