slava.energy: UK renewable energy projects
Coombe Farm
REPD record 7114. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 7.5 MW
- Status
- Planning Permission Expired
- Operator
- KWTN Solar
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 17/03395/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-02-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-08-18: Planning Application Submitted
- 2017-10-27: Planning Permission Granted
- 2020-10-13: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7114. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.