slava.energy: UK renewable energy projects
Penwortham Sub Station
REPD record 7119. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 50 MW
- Status
- Planning Permission Expired
- Operator
- Statera Energy
- County
- Lancashire
- Region
- North West
- Country
- England
- Planning authority
- South Ribble
- Planning reference
- 07/2017/2821/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-08-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-09-18: Planning Application Submitted
- 2020-11-16: Planning Permission Expired
- 2021-05-14: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7119. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.