Kells Substation
REPD record 7160. Status: Appeal Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- not held by REPD
- Status
- Appeal Granted
- Operator
- Kells Bes (ABO Wind)
- County
- Co. Tyrone
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Antrim and Newtownabbey
- Planning reference
- LA03/2018/0984/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-04-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2018-10-25: Planning Application Submitted
- 2019-03-22: Planning Permission Refused
- 2019-03-27: Appeal Lodged
- 2019-11-27: Appeal Granted
- 2019-11-27: Planning Permission Granted
- 2024-11-27: Planning Permission Expired