slava.energy: UK renewable energy projects
Wilnecote Landfill Site
REPD record 718. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Landfill Gas
- Capacity
- 1 MW
- Status
- Operational
- Operator
- Biffa
- County
- Staffordshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Tamworth
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2005-09-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 1999-05-19: Planning Application Submitted
- 2000-02-18: Planning Permission Granted
- 2000-06-08: Operational
- 2019-02-18: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 718. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.