slava.energy: UK renewable energy projects
Tesco Wombwell Lane
REPD record 7225. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.2 MW
- Status
- Operational
- Operator
- Batchelor Electrical
- County
- South Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Barnsley
- Planning reference
- 2019/0194
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-07-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-07-09: Planning Permission Expired
- 2019-03-12: Planning Application Submitted
- 2019-07-09: Planning Permission Granted
- 2020-01-20: Under Construction
- 2020-04-01: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7225. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.