Tesco Superstore Shripney Road
REPD record 7229. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.2 MW
- Status
- Operational
- Operator
- Batchelor Electrical
- County
- West Sussex
- Region
- South East
- Country
- England
- Planning authority
- Arun
- Planning reference
- BR/60/19/PD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-07-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-03-11: Planning Permission Expired
- 2019-03-11: Planning Application Submitted
- 2020-02-01: Under Construction
- 2020-05-01: Operational
- 2021-03-11: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7229. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.