slava.energy: UK renewable energy projects
Land North of Actrees Solar Farm
REPD record 7230. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Operational
- Operator
- SMS
- County
- Gloucestershire
- Region
- South West
- Country
- England
- Planning authority
- Stroud
- Planning reference
- S.19/0372/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-08-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-03-07: Planning Application Submitted
- 2022-10-10: Planning Permission Expired
- 2025-05-01: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7230. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.