Patteson Court Landfill Site
REPD record 724. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Landfill Gas
- Capacity
- 1.8 MW
- Status
- Operational
- Operator
- Biogeneration & Biffa
- County
- Surrey
- Region
- South East
- Country
- England
- Planning authority
- Reigate and Banstead
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2005-10-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 1994-01-12: Planning Application Submitted
- 1994-03-07: Planning Permission Granted
- 1996-07-01: Operational
- 2012-03-07: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 724. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.