slava.energy: UK renewable energy projects
Amazon Omega Business Park
REPD record 7248. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.5 MW
- Status
- Operational
- Operator
- Amazon UK Services & Push Energy
- County
- Cheshire
- Region
- North West
- Country
- England
- Planning authority
- Warrington
- Planning reference
- 2018/33362
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-01-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-02-20: Planning Application Submitted
- 2019-04-30: Planning Permission Granted
- 2020-01-01: Operational
- 2022-05-14: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7248. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.