slava.energy: UK renewable energy projects
The Grange
REPD record 7256. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 49.9 MW
- Status
- Operational
- Operator
- Lightsource BP
- County
- Nottinghamshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Newark and Sherwood
- Planning reference
- 19/01408/FULM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2021-04-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-08-09: Planning Application Submitted
- 2020-07-26: Under Construction
- 2021-04-01: Operational
- 2022-11-28: Planning Permission Expired
- 2023-06-28: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7256. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.