Streetfield Farm
REPD record 7258. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 18.3 MW
- Status
- Operational
- Operator
- Lightsource BP
- County
- Warwickshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Rugby
- Planning reference
- R19/0259
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-02-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-02-07: Planning Application Submitted
- 2019-06-19: Planning Permission Granted
- 2022-07-18: Planning Permission Expired
- 2022-12-01: Operational
Open this area on the map