slava.energy: UK renewable energy projects
Eurofoods Building
REPD record 7262. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.6 MW
- Status
- Planning Permission Granted
- Operator
- Eurofoods Group
- County
- West Glamorgan
- Region
- Wales
- Country
- Wales
- Planning authority
- Swansea
- Planning reference
- 2019/0331/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-04-09
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-02-13: Planning Application Submitted
- 2019-04-09: Planning Permission Granted
- 2024-04-09: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7262. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.