Mayton Wood Landfill Site
REPD record 728. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Landfill Gas
- Capacity
- 1.5 MW
- Status
- Operational
- Operator
- Combined Landfill Projects (CLP)
- County
- Norfolk
- Region
- Eastern
- Country
- England
- Planning authority
- Broadland
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2005-03-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 1993-12-10: Planning Application Submitted
- 1994-04-14: Planning Permission Granted
- 1996-03-01: Operational