slava.energy: UK renewable energy projects
Sundon Substation
REPD record 7283. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Revised
- Operator
- Pivot Power
- County
- Bedfordshire
- Region
- Eastern
- Country
- England
- Planning authority
- Central Bedfordshire
- Planning reference
- CB/19/00200/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-04-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-01-23: Planning Application Submitted
- 2022-04-30: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7283. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.