slava.energy: UK renewable energy projects
Volmary Site
REPD record 7298. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.2 MW
- Status
- Operational
- Operator
- Volmary
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- Fenland
- Planning reference
- F/YR19/0063/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-07-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-01-24: Planning Application Submitted
- 2019-03-22: Planning Permission Granted
- 2019-03-31: Under Construction
- 2019-07-31: Operational
- 2022-03-20: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7298. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.