Aurora Solar Farm
REPD record 7384. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 32 MW
- Status
- Under Construction
- Operator
- Low Carbon UK Solar Investment Company
- County
- Oxfordshire
- Region
- South East
- Country
- England
- Planning authority
- West Oxfordshire
- Planning reference
- 19/02516/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-03-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-09-24: Planning Application Submitted
- 2020-02-10: Planning Permission Granted
- 2021-04-26: Under Construction
- 2023-03-23: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7384. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.