East Codford Solar Farm Extension Phase 3
REPD record 7405. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 18 MW
- Status
- Operational
- Operator
- Centrica Plc
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- 19/03576/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-06-13
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-04-08: Planning Application Submitted
- 2020-12-18: Planning Permission Granted
- 2022-04-25: Under Construction
- 2022-08-02: Planning Permission Expired
- 2022-09-01: Operational
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7405. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.