Keele University
REPD record 7409. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.4 MW
- Status
- Operational
- Operator
- Keele University
- County
- Staffordshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Newcastle-under-Lyme
- Planning reference
- 18/00934/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-05-12
Status history
Dated status events as published by REPD, release Q3 2026.
- 2018-12-20: Planning Application Submitted
- 2019-02-20: Planning Permission Granted
- 2020-12-02: Under Construction
- 2022-04-29: Operational
- 2022-08-30: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7409. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.