Langford Solar Farm
REPD record 7451. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 35 MW
- Status
- Operational
- Operator
- JBM Solar Projects
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- Mid Devon
- Planning reference
- 19/01679/MFUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-07-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-10-10: Planning Application Submitted
- 2021-09-23: Planning Permission Refused
- 2022-02-17: Appeal Lodged
- 2022-12-05: Appeal Granted
- 2022-12-05: Planning Permission Granted
- 2025-07-02: Operational
- 2025-12-05: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7451. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.