Harker Grid Sub Station
REPD record 7462. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Planning Permission Expired
- Operator
- Pivot Power
- County
- Cumbria
- Region
- North West
- Country
- England
- Planning authority
- Cumberland
- Planning reference
- 19/0371
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-09-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-05-08: Planning Application Submitted
- 2019-07-10: Planning Permission Granted
- 2022-07-10: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7462. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.