Bonnyrigg
REPD record 747. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Landfill Gas
- Capacity
- 2.2 MW
- Status
- Operational
- Operator
- Natural Power
- County
- Lothian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Midlothian
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2001-10-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2000-02-10: Planning Application Submitted
- 2000-03-29: Planning Permission Granted
- 2001-07-15: Operational
- 2010-03-29: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 747. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.