slava.energy: UK renewable energy projects
Thorpe Bank Solar Farm
REPD record 7546. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 32 MW
- Status
- Revised
- Operator
- Lightsource BP
- County
- County Durham
- Region
- North East
- Country
- England
- Planning authority
- Stockton-on-Tees
- Planning reference
- 20/2131/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-05-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-09-29: Planning Application Submitted
- 2020-12-11: Planning Permission Granted
- 2023-12-11: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7546. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.