slava.energy: UK renewable energy projects
Home Farm
REPD record 7557. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 25 MW
- Status
- Planning Permission Granted
- Operator
- Canadian Solar & Novergy
- County
- Worcestershire
- Region
- West Midlands
- Country
- England
- Planning authority
- Tewkesbury
- Planning reference
- W/23/01011/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-02-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-06-27: Planning Application Submitted
- 2025-06-16: Planning Permission Granted
- 2028-06-16: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7557. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.