South Shore Holiday Village
REPD record 7559. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.4 MW
- Status
- Operational
- Operator
- East Riding of Yorkshire Council
- County
- Humberside
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- East Riding of Yorkshire
- Planning reference
- 19/01883/REG3
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-03-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-06-25: Planning Application Submitted
- 2020-12-14: Planning Permission Granted
- 2021-03-01: Under Construction
- 2021-05-18: Operational
- 2022-09-24: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7559. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.