slava.energy: UK renewable energy projects
Sheirdrim Renewable Energy Development - Battery
REPD record 7585. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 38 MW
- Status
- Appeal Refused
- Operator
- ScottishPower Renewables
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Scottish Government (S36)
- Planning reference
- ECU00001957
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-07-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-10-10: Planning Application Submitted
- 2021-03-21: Appeal Lodged
- 2023-06-26: Appeal Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7585. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.