REPD record 7595. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 3 MW
- Status
- Under Construction
- Operator
- Ednie Farms
- County
- Grampian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Aberdeenshire
- Planning reference
- APP/2019/2653
- Turbines
- 2
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-02-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-12-03: Planning Application Submitted
- 2020-12-07: Planning Permission Refused
- 2021-07-21: Appeal Granted
- 2021-07-21: Planning Permission Granted
- 2023-02-06: Under Construction
- 2024-07-21: Planning Permission Expired