slava.energy: UK renewable energy projects
St Fergus Renewable Energy Park
REPD record 7596. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Under Construction
- Operator
- Ednie Farms
- County
- Grampian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Aberdeenshire
- Planning reference
- APP/2019/2653
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-02-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-12-03: Planning Application Submitted
- 2020-12-07: Planning Permission Refused
- 2021-01-29: Appeal Lodged
- 2021-07-21: Appeal Granted
- 2021-07-21: Planning Permission Granted
- 2023-02-06: Under Construction
- 2024-07-21: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7596. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.