Lapwing Fen 2 - Battery Storage Plant
REPD record 7614. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 250 MW
- Status
- Under Construction
- Operator
- Tribus Clean Energy
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- King's Lynn and West Norfolk
- Planning reference
- 19/02004/FM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-06-08
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-11-25: Planning Application Submitted
- 2020-04-27: Planning Permission Granted
- 2022-06-01: Under Construction
- 2023-03-19: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7614. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.