slava.energy: UK renewable energy projects
Kenyon Way
REPD record 7738. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.9 MW
- Status
- Under Construction
- Operator
- Private Developer
- County
- Greater Manchester
- Region
- North West
- Country
- England
- Planning authority
- Salford
- Planning reference
- 20/74960/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-02-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-03-05: Planning Application Submitted
- 2020-07-24: Planning Permission Granted
- 2023-07-01: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7738. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.