slava.energy: UK renewable energy projects
Patrickston Farm
REPD record 7785. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 15 MW
- Status
- Planning Permission Expired
- Operator
- Green Energy International
- County
- Stirling
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Stirling
- Planning reference
- 19/00915/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2021-02-07
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-01-27: Planning Application Submitted
- 2020-05-05: Planning Permission Granted
- 2023-04-05: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7785. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.