slava.energy: UK renewable energy projects
Chancerygate Way
REPD record 7792. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.3 MW
- Status
- Abandoned
- Operator
- Oakapple Renewable Energy
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Rushmoor
- Planning reference
- 20/00006/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2021-02-07
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-01-06: Planning Application Submitted
- 2023-02-07: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7792. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.