slava.energy: UK renewable energy projects
James Cropper Effluent Plant
REPD record 7810. Status: Planning Application Withdrawn.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1 MW
- Status
- Planning Application Withdrawn
- Operator
- Ellergreen Estate
- County
- Cumbria
- Region
- North West
- Country
- England
- Planning authority
- Westmorland and Furness
- Planning reference
- SL/2019/1027
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-06-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-12-17: Planning Application Submitted
- 2020-01-21: Planning Application Withdrawn
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7810. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.