Cornharrow Wind Farm Battery
REPD record 7849. Status: Appeal Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- not held by REPD
- Status
- Appeal Granted
- Operator
- Energiekontor UK
- County
- Dumfries and Galloway
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Dumfries and Galloway
- Planning reference
- 20/0159/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-10-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-02-19: Planning Application Submitted
- 2020-08-21: Appeal Lodged
- 2021-06-01: Planning Permission Refused
- 2022-03-21: Appeal Granted
- 2022-03-21: Planning Permission Granted
- 2025-03-21: Planning Permission Expired