slava.energy: UK renewable energy projects
Morfa Pingett
REPD record 7914. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.6 MW
- Status
- Revised
- Operator
- Richard Thomas Associates
- County
- Carmarthenshire
- Region
- Wales
- Country
- Wales
- Planning authority
- Carmarthenshire
- Planning reference
- S/40618
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-06-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-05-21: Planning Application Submitted
- 2021-03-11: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7914. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.