slava.energy: UK renewable energy projects
Perth Wastewater Treatment Works (Extension)
REPD record 7915. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.3 MW
- Status
- Operational
- Operator
- Scottish Water
- County
- Perth and Kinross
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Perth and Kinross
- Planning reference
- 20/00540/FLL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2021-05-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-05-18: Planning Application Submitted
- 2020-09-08: Planning Permission Granted
- 2021-05-17: Operational
- 2023-09-07: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7915. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.