Redcar Energy Centre
REPD record 7927. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- EfW Incineration
- Capacity
- 49.9 MW
- Status
- Planning Permission Granted
- Operator
- Redcar Holdings
- County
- Cleveland
- Region
- North East
- Country
- England
- Planning authority
- Redcar and Cleveland
- Planning reference
- R/2020/0411/FFM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-11-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-08-03: Planning Application Submitted
- 2021-01-27: Planning Permission Granted
- 2024-01-27: Planning Permission Expired