Drummond Moor Landfill
REPD record 799. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Landfill Gas
- Capacity
- 2 MW
- Status
- Operational
- Operator
- Waste Recycling Group
- County
- Lothian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Midlothian
- Planning reference
- 040081FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-05-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2004-10-18: Planning Application Submitted
- 2004-12-22: Planning Permission Granted
- 2004-12-23: Under Construction
- 2005-04-01: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 799. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.