slava.energy: UK renewable energy projects
Netley Landfill Site, Hampshire (Extension)
REPD record 800. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Landfill Gas
- Capacity
- 1.2 MW
- Status
- Operational
- Operator
- Hampshire Waste Services& ONYX & Power Plant Services
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Eastleigh
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2010-08-06
Status history
Dated status events as published by REPD, release Q3 2026.
- 1995-06-16: Planning Application Submitted
- 1996-01-26: Planning Permission Granted
- 1997-06-18: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 800. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.